RES - Powering Tomorrows World....  
 
Nine Canyon Wind Farm Phase II

Nine Canyon Wind Farm, Phase II, Tri-Cities, SE Washington

A 15.6MW extension to the Nine Canyon wind farm was completed in December 2003. It comprises an additional 12 Bonus 1.3MW wind turbines, and brings the total installed capacity at the Nine Canyon site to 63.7MW, still the largest public-owned project in the United States.

As with Phase I, the extension was built on a turnkey contract by RES (USA) for Energy Northwest and it achieved substantial completion two weeks ahead of schedule.

Information about the Project
line

Owner: Energy Northwest
Turnkey Construction Contractor: Renewable Energy Systems (USA) Inc
Operation and Maintenance Contractor: Energy Northwest
Installed Capacity: 15.6 MW
Number of Turbines: 12
Turbine Rating: 1,300 kW
Turbine Type: Bonus, Active Stall

 

 
 

Home | RES Group | Wind Farms | Wind Power | Heat and Power | Beaufort Court | News | Contact Us
  Copyright © 2000 - Renewable Energy Systems Ltd. All rights reserved.   Terms of Use