Sweetwater Phase II

Sweetwater Phase II, Texas

RES were responsible for the design and construction (including turbine
erection) of this 91.5MW wind farm.

The project was constructed from start to finish, including installation of two substations and eight miles of overhead line, within four and a half months of notice to proceed.

It became operational in February 2005.


Information about the Project

Owner: Sweetwater II
Turnkey Construction Contractor: RES America Construction
Operation & Maintenance Contractor: GE
Installed Capacity: 91.5 MW
Number of Turbines: 61
Turbine Rating: 1,500 kW
Turbine Type: GE 1.5MW
   

 