Trois Sources Wind Farm
The Trois Sources wind farm
project is situated in the south-west region of the Meuse department
(55), not far from the county border with the Haute Marne (52). It lies
on the territory of the villages of Bonnet and Houdelaincourt.
The project is developed by EOLE-RES and comprises 18 x 2 MW turbines,
resulting in an installed capacity of 36 MW.
The estimated energy to be produced by the Trois Sources wind farm is
equivalent to an annual saving of approximately 25 000 tonnes of CO² and
will cover the electricity needs of over 33 000 people.
Information about the Project

| Owner: |
CEPE des Trois Sources |
| Turnkey Construction Contractor: |
CEPE des Trois Sources |
| Operation & Maintenance Contractor: |
EOLE-RES SA |
| Installed Capacity: |
36 MW |
| Number of Turbines: |
18 |
| Turbine Rating: |
2,000 kW |
| Turbine Type: |
To be confirmed |
| |
|
|